Establishing a broiler farm is a multi-year investment, and most of its costly decisions are made before the first foundation is poured: where to build, how many houses of what size, and which ventilation, heating, feed and water systems. Mistakes at this stage are hard to correct after construction. For this reason, the Ross Broiler Management Handbook (2025) recommends consulting a specialist at the design stage, before construction begins.
This article reviews the stages of construction in order, lists for each stage the information the investor should prepare, and explains at which stages Toyooran Sanat Pouya’s consulting and fit-out service comes in. Technical data are quoted from the Ross handbook. On permits, only the general path as set out in official sources is explained; the exact documents and rules for each case are determined by the permit-issuing authority of the county concerned.
| Stage | Main output |
|---|---|
| 1. Feasibility and scheme definition | Target capacity, number of houses, initial capital estimate |
| 2. Land selection and inquiry | Confirmation that the unit can be sited on that land |
| 3. Establishment permit | Permission to build from the official authority |
| 4. Structural and services design | Construction drawings, calculation report, equipment list |
| 5. Shed construction | An insulated, airtight structure |
| 6. House fit-out | Feed and water lines, ventilation, inlets, heating, control |
| 7. Commissioning and operating licence | A house ready for chick placement and permission to start production |
Until the land’s suitability for siting is confirmed, detailed design and equipment purchase carry a risk of rework.
The starting point is a precise definition of the scheme: broiler production at what capacity per cycle, in how many houses, with what level of automation. Ross lists the following for determining house size and number:
Ross notes that stocking density depends on local regulations, climate, equipment and local economics, so there is no single figure for everywhere. An initial capital estimate is also made at this stage. The main components of fit-out cost are covered in the article Cost and components of equipping a house.
What the investor prepares: the intended capacity, the type of production, an approximate budget, a timetable, and whether a new house is to be built or an existing house renovated.
Ross sets out several criteria for house location and design that relate directly to land selection:
Practical advice: before buying or leasing land, inquire with the official authority whether a poultry unit can be sited on that plot. Buffer zones and permitted distances from other units are set by the current rules of the area, and this article does not give a figure for them.
In the official service register of the Fars Province Agricultural Jihad Organisation, the services “issuing and renewing establishment permits”, “issuing and renewing operating licences”, “issuing and renewing health licences” and “reviewing and approving site plans” for industrial and semi-industrial livestock units are listed as electronic services via the eagri.maj.ir system. This list makes two points clear:
Many business permits are now applied for through the National Permits Portal (mojavez.ir). According to the official guide to submitting applications on this portal, each permit’s page shows the conditions, documents, fees and statutory issuing time; some documents are themselves separate permits; and if the required documents are not uploaded after an application is submitted, the application is rejected after 24 hours. It is therefore best to have all documents ready before submitting an application.
What the investor prepares: identity documents, documents of ownership or the right to use the land, the land’s geographical location and a description of the scheme. The complete, up-to-date list of documents is published on that permit’s page in the National Permits Portal and by the county Agricultural Jihad office.
Once the land and permit situation is clear, detailed design begins. Ross highlights several design requirements:
The local climate determines the type and size of the ventilation system; the calculation method is covered in Calculating house ventilation capacity. Frequent mistakes at this stage, such as unsuitable width and poor insulation, are reviewed in Common mistakes in poultry house design.
If structural construction and equipment installation are separated, poor coordination between the shed builder and the equipment installer can lead to rework. In the poultry house fit-out and renovation service, Toyooran Sanat Pouya carries out both in a single process:
According to the service page, structures are calculated on the basis of the National Building Regulations and Standard 2800 for the climate of each region.
Before the first chick placement, all systems must be tested. Ross sets several specific requirements for this stage:
After construction and fit-out are complete, an operating licence must be obtained from the authority that issued the establishment permit.
According to the service page, Toyooran Sanat Pouya’s development, operation and efficiency consulting service covers economic feasibility consulting and machinery selection and provides guidance on the Agricultural Jihad permit path; permits are issued by the official authority. The service is carried out in three steps:
For a new unit, this service helps with decisions at stages 1 to 4, and the house fit-out service carries out stages 5 to 7. The exact scope of work for each scheme is specified in the technical proposal for that scheme.

Standard capacity: 2.5 to 30 tonnes (custom-built up to 100 tonnes)
View productWith defining the scheme (capacity, number of houses, budget) and inquiring about the land’s suitability for siting. Ross recommends checking local rules at the earliest opportunity and consulting a specialist at the design stage, before construction begins.
The establishment permit is permission to build, and the operating licence is issued after construction and fit-out are complete. In the Agricultural Jihad service register, these are listed as two separate services. The exact documents are published on that permit’s page in the National Permits Portal.
All systems, especially emergency power and alarms, heating and drinking. According to Ross, the house is warmed and stabilised at least 24 hours before chick arrival, humidity should be 60 to 70 percent, and water lines should be flushed 1 to 2 hours before arrival.
According to the service page: economic feasibility, machinery selection and guidance on the Agricultural Jihad permit path (permits are issued by the official authority); and, in the house fit-out service, structural design, shed construction and equipment installation up to handover of a house ready for chick placement.
To begin the review, send the following information: the province and county of the site, the land situation (ownership, area, access to power, water and fuel), the intended capacity and number of houses, the current permit status and the timetable. Based on this information, a Toyooran Sanat Pouya specialist will recommend the next steps. See the full service description on the consulting and efficiency improvement page.
Send the land and scheme details.
Request construction consulting
Topic: House equipment
Category: Engineering technical guide
Tags: Poultry farm construction, Poultry farm permit, Broilers, Consultation
Published: 2026-10-15